 |
|
Leamington Spa Station (GWR)
Leaminton Station is located on Old Warwick Road towards the
southern edge of the town centre. The station was opened in 1852 by the Great
Western Railway as part of the Birmingham to Oxford line. Its opening compelled
the LNWR to build in 1854 their own Leamington station which was located
adjacent to the GWR station. In 1864 a link was made between the GWR line and
the LNWR after which a good deal of goods traffic was interchanged between the
two lines.
By the late 1920s there were over one million men
unemployed in the UK and in an attempt to reduce this figure the government
introduced the Development (Loan Guarantee and Grants) Act 1929.
This Bill provided financial assistance to public utilities for what would
otherwise be un-ruminative Capital expenditure schemes in the form of annual
low interest grants and also grants to defray, in whole or in part, the
interest payments on any Loan (with a 15 year limit).
As a result of this scheme, the Great Western developed an
extensive improvement programme across its network. In the Warwickshire Area
this included quadrupling the Birmingham Main Line approaches (1933), New Goods
Facilities in Birmingham (1933) and reconstruction of Leamington Spa Station
(1938). The first Leamington Spa Station had been built in 1853, but had been
modified piecemeal over the years, with extra buildings, removal of the overall
train shed roof, additional platform length and construction of a bay platform.
The planned new station would have wider platforms of standard height protected
by new longer canopies and connected by a new 15 wide passenger subway
with electric lifts to each platform for luggage. A new approach road was to be
constructed to provide access at subway level and an impressive modern
Art Deco style, three storey station building faced with Portland
stone and granite would provide additional facilities for both passengers and
staff. Electric lighting would be provided to all buildings and the subway,
while modern gas lighting was to be provided to the platforms and station
approach roads.
Normal traffic operation and passenger access was required to
continue during the station reconstruction work which resulted in the work
being carried out in a series of stages and taking almost two years to
complete. A temporary booking office pavilion was built in the forecourt and
maintained almost to the end. The limited working space on the up platform
required all surplus materials from the excavation and demolition on this side
to be removed by rail. The initial stage was to construct the new subway,
excavate the forecourt, demolish the down side buildings and build new
retaining walls for the down platform. This was carried out by E.C.Jordan of
Newport, under a contract worth almost £20,000. Approximately 18,000
cubic yards of excavation were removed to form a forecourt, which extended over
¾ acre with a separate entrance and exit and 27,000 sq feet of surfaced
roadway and parking space. During the excavation water was encountered below
the platforms necessitating extra drainage and the provision of a 2
cavity behind the walls.
Holliday & Greenwood were given a contract worth
£35,000 to erect new station buildings and carry out platform
alterations. The building was a prefabricated steel framed structure, sheathed
with brickwork and externally faced with white Portland stone above a
contrasting polished granite plinth. This granite plinth continued into the
booking office, with tiling above, while the subway was tiled through out
including the non-slip floor. The granite plinth was also retained on the 1st
floor platform side with the Portland stone facing on the pillars and
restaurant façade, but English bond brickwork on the remaining walls.
The new platforms were paved with precast slabs obtained from the GWR depot at
Taunton. The building roofs were flat surrounded by low parapets, while the new
canopies were conventional Great Western design, with zinc sheets over a
shallow reverse slope steelwork frame supported on cast iron pillars. The down
platform canopy had glass sections to provided natural light where it adjoined
the station building.
To the left of the main entrance on the ground floor of the new
station building (with direct access to the forecourt) were; the parcels
office, cloak room, cycle store and the refreshment room cellar. To the right
was the booking office and the entrance to the former passenger subway, which
on completion was converted to a public footpath allowing the removal of the
footbridge at the west end of the station. At platform level on the first floor
was a store, the refreshment room, down side waiting room and lavatories, pay
clerks office, bookstall, telegraph office, station masters office, staff
office and mess room. On the up platform was a second refreshment room, a
bookstall, lavatories and a waiting room and on the top floor of the station
building was further office accommodation and at least one staff flat. The
reconstruction work was completed in 1939 and would have been the template for
several other stations, but for the start of the Second World War. The
construction quality is confirmed by the fact that after approximately eighty
years the station buildings at Leamington Spa Station have needed little
alteration.
Anyone interested in the history of Leamington station must
obtain copies of the Great Western Railway
Journal No 57 and No 58, edited by John Copsey. The two Journals contain
articles by Chris Turner and John Copsey which must be regarded as the most
extensive history of the station yet published. Many of the captions used
throughout this website's Leamington pages are inspired by or use their
exhaustive information. Local enthusiasts and historian's should count their
blessings that not only are they privileged to be able to see the railway scene
captured through HJ Stretton-Ward's lens but that they are accompanied by
Chris' and John's superb captions and research.
Exterior views of Leamington's original station
Platform and lineside views of Leamington's original
station
Rebuilding of the station
The main station building viewed from Old Warwick Road
The down platform
The up platform
The rebuilt Leamington station
External and internal views of Leamington's new station
building
Platform and lineside views of Leamington station's up
platform
Platform and lineside views of Leamington station's down
platform
Leamington station's goods yard and sidings
Rebuilding of bridges on the southern approaches to
Leamington station
Miscellaneous
Maps and Layout Drawings
General maps and schematics
1852 Map
1886 Maps
1925 Maps
1939 Maps

|