|  |  
						 
						 
						 
						   
							 | London North Western
								  Railway:  Midland
								  Railway:
  Stratford
								  Midland Junction Railway
 |  
 | Kilsby TunnelNorthamptonshireKilsby Tunnel is a railway tunnel on the London and
						Birmingham Railway which was opened in 1838 and forms part of West Coast Main
						Line railway. The tunnel is located near the village of Kilsby in
						Northamptonshire approximately 5 miles south-east of Rugby and is 2,426 yards
						in length. There are ten ventilating shafts each of nine feet in diameter, and
						two large shafts of sixty feet diameter, these latter being surmounted by
						impressive castellated towers . The tunnel took far longer, and cost
						significantly more money to build than had been anticipated. This was because
						the tunnel roof collapsed and the tunnel flooded unexpectedly due to quicksand
						which trial borings into the hill had not revealed. The excess water from the
						quicksand had to be pumped out, a process which took some eight months. This
						shouldn't have been a complete surprise as similar problems were encountered
						with nearby Blisworth tunnel on the Grand Union Canal a few decades earlier.
						The length of time it took to build the tunnel delayed the opening of the
						London and Birmingham Railway resulting in a stage coach service to be used to
						move passengers between the two completed sections of the line. It took three
						years, and cost £320,000 to build which was three times the original
						estimate. It is reported that approximately 30 million bricks were used in
						construction. Around the turn of the century the inner lining was giving cause
						for concern, the remedy being to reline with Staffordshire blue brick. It was
						designed and engineered by Robert Stephenson and it is today the 18th longest
						tunnel on the British railway system. The construction of the tunnel has been recorded by Samuel
						Smiles in his 1879 autobiography of the Stephenson's. The section relevant to
						the tunnel, pages 246 to 252, is provided below. LIVES of the ENGINEERSGEORGE AND ROBERT
						STEPHENSON
 BY SAMUEL SMILES (1879)Though not the largest, this is in many respects one of the
						most interesting works of the kind in England. It is about 2400 yards long, and
						runs at an average depth of about 160 feet below the surface. The ridge under
						which it extends is of considerable extent, the famous battle of Naseby having
						been fought upon one of the spurs of the same high ground about seven miles to
						the eastward. Previous to the letting of the contract, the character of
						the underground soil was examined by trial-shafts. The tests indicated that it
						consisted of shale of the lower oolite, and the works were let accordingly. But
						they had scarcely been commenced when it was discovered that, at an interval
						between the two trial-shafts which had been sunk, about 200 yards from the
						south end of the tunnel, there existed an extensive quicksand under a bed of
						clay 40 feet thick, which the borings had escaped in the most singular manner.
						At the bottom of one of these shafts the excavation and building of the tunnel
						were proceeding, when the roof at one part suddenly gave way, a deluge of water
						burst in, and the party of workmen with the utmost difficulty escaped with
						their lives. They were only saved by means of a raft, on which they were towed
						by one of the engineers swimming with the rope in his mouth to the lower end of
						the shaft, out of which they were safely lifted to the daylight. The works were
						of course at that point immediately stopped. The contractor, who had undertaken the construction of the
						tunnel, was so overwhelmed by the calamity, that, though he was relieved by the
						Company from his engagement, he took to his bed and shortly after died.
						Pumping-engines were then erected for the purpose of draining off the water,
						but for a long time it prevailed, and sometimes even rose in the shaft. The
						question then presented itself, whether in the face of so formidable a
						difficulty, the works should be proceeded with or abandoned. Robert Stephenson
						sent over to Alton Grange for his father, and the two took serious counsel
						together. George was in favour of pumping out the water from the top by
						powerful engines erected over each shaft, until the water was mastered. Robert
						concurred in that view, and although other engineers pronounced strongly
						against the practicability of the scheme and advised its abandonment, the
						directors authorised him to proceed; and powerful steam-engines were ordered to
						be constructed and delivered without loss of time. In the mean time, Robert suggested to his father the
						expediency of running a drift along the heading from the south end of the
						tunnel, with the view of draining off the water in that way. George said he
						thought it would scarcely answer, but that it was worth a trial, at all events
						until the pumping-engines were got ready. Robert accordingly gave orders for
						the drift to be proceeded with. The excavators were immediately set to work;
						and they were very soon close upon the sand bed. One day, when the engineer,
						his assistants, and the workmen were clustered about the open entrance of the
						drift-way, they heard a sudden roar as of distant thunder. It was hoped that
						the water had burst infor all the workmen were out of the drift,and
						that the sand bed would now drain itself off in a natural way. Instead of
						which, very little water made its appearance; and on examining the inner end of
						the drift, it was found that the loud noise had been caused by the sudden
						discharge into it of an immense mass of sand, which had completely choked up
						the passage, and prevented the water from flowing away. The engineer now found that there was nothing for it but to
						sink numerous additional shafts over the line of the tunnel at the points at
						which it crossed the quicksand, and endeavour to master the water by sheer
						force of engines and pumps. The engines erected, possessed an aggregate power
						of 160 horses; and they went on pumping for eight successive months, emptying
						out an almost incredible quantity of water. It was found that the water, with
						which the bed of sand extending over many miles was charged, was to a certain
						degree held back by the particles of the sand itself, and that it could only
						percolate through at a certain average rate. It appeared in its flow to take a
						slanting direction to the suction of the pumps, the angle of inclination
						depending upon the coarseness or fineness of the sand, and regulating the time
						of the flow. Hence the distribution of the pumping power at short intervals
						along the line of the tunnel had a much greater effect than the concentration
						of that power at any one spot. It soon appeared that the water had found its
						master. Protected by the pumps, which cleared a space for the engineering
						operationscarried on in the midst, as it were, of two almost
						perpendicular walls of water and sand on either sidethe workmen proceeded
						with the building of the tunnel at numerous points. Every exertion was used to
						wall in the dangerous parts as quickly as possible; the excavators and
						bricklayers labouring night and day until the work was finished. Even while
						under the protection of the immense pumping power above described, it often
						happened that the bricks were scarcely covered with cement ready for the
						setting, here they were washed quite clean by the streams of water which poured
						from overhead. The men were accordingly under the necessity of holding over
						their work large whisks of straw and other appliances to protect the bricks and
						cement at the moment of setting. The quantity of water pumped out of the sand bed during
						eight months of incessant pumping, averaged 2,000 gallons per minute, raised
						from an average depth of 120 feet. It is difficult to form an adequate idea of
						the bulk of the water thus raised, but it may be stated that if allowed to flow
						for three hours only, it would fill a lake one acre square to the depth of one
						foot, and if allowed to flow for one entire day it would fill the lake to over
						eight feet in depth, or sufficient to float vessels of 100 tons. The water
						pumped out of the tunnel while the work was in progress would be nearly
						equivalent to the contents of the Thames at high water, between London and
						Woolwich. It is a curious circumstance that notwithstanding the quantity thus
						removed, the level of the surface of the water in the tunnel was only lowered
						about 2½ to 3 inches per week, proving the vast area of the quicksand,
						which probably extended along the entire ridge of land under which the railway
						passed. The cost of the line was greatly increased by the
						difficulties encountered at Kilsby. The original estimate for the tunnel was
						only £99,000; but before it was finished it had cost more than £100
						per lineal yard forward, or a total of nearly £300,000. The expenditure
						on the other parts of the line also greatly exceeded the amount first set down
						by the engineer; and before the works were finished it was more than doubled.
						The land cost three times more than the estimate; and the claims for
						compensation were enormous. Although the contracts were let within the
						estimates, very few of the contractors were able to complete them without the
						assistance of the Company, and many became bankrupt. The magnitude of the works, which were unprecedented in
						England, was one of the most remarkable features in the undertaking. The
						following striking comparison has been made between this railway and one of the
						greatest works of ancient times. The Great Pyramid of Egypt was, according to
						Diodorus Siculus, constructed by 300,000according to Herodotus, by
						100,000men. It required for its execution twenty years, and the labour
						expended upon it has been estimated as equivalent to lifting 15,733,000,000 of
						cubic feet of stone one foot high. Whereas, if the labour expended in
						constructing the London and Birmingham Railway be in like manner reduced to one
						common denomination the result is 25,000,000,000 of cubic feet more than was
						lifted for the Great Pyramid; and yet the English work was performed by about
						20,000 men in less than five years. And whilst the Egyptian work was executed
						by a powerful monarch concentrating upon it the labour and capital of a great
						nation, the English railway was constructed, in the face of every conceivable
						obstruction and difficulty, by a company of private individuals out of their
						own resources, without the aid of Government or the contribution of one
						farthing of public money. The labourers who executed this formidable work were in many
						respects a remarkable class. The railway navvies, as they are
						called, were men drawn by the attraction of good wages from all parts of the
						kingdom; and they were ready for any sort of hard work. Some of the best came
						from the fen districts of Lincoln and Cambridge, where they had been trained to
						execute works of excavation and embankment. These old practitioners formed a
						nucleus of skilled manipulation and aptitude, which rendered them of
						indispensable utility in the immense undertakings of the period. Their
						expertness in all sorts of earthworks, in embanking, boring, and
						well-sinkingtheir practical knowledge of the nature of soils and rocks,
						the tenacity of clays, and the porosity of certain stratificationswere
						very great; and, rough-looking though they were, many of them were as important
						in their own department as the contractor or the engineer. During the railway-making period the navvy wandered about
						from one public work to anotherapparently belonging to no country and
						having no home. He usually wore a white felt hat with the brim turned up, a
						velveteen or jean square-tailed coat, a scarlet plush waistcoat with little
						black spots, and a bright-coloured kerchief round his herculean neck, when, as
						often happened, it was not left entirely bare. His corduroy breeches were
						retained in position by a leathern strap round the waist, and were tied and
						buttoned at the knee, displaying beneath a solid calf and foot encased in
						strong high-laced boots. Joining together in a butty gang, some ten
						or twelve of these men would take a contract to cut out and remove so much
						dirtas they denominated earth-cuttingfixing their price
						according to the character of the stuff, and the distance to which
						it had to be wheeled and tipped. The contract taken, every man put himself on
						his mettle; if any was found skulking, or not putting forth his full working
						power, he was ejected from the gang. Their powers of endurance were
						extraordinary. In times of emergency they would work for 12 and even 16 hours,
						with only short intervals for meals. The quantity of flesh-meat which they
						consumed was something enormous; but it was to their bones and muscles what
						coke is to the locomotivethe means of keeping up the steam. They
						displayed great pluck, and seemed to disregard peril. Indeed the most dangerous
						sort of laboursuch as working horse-barrow runs, in which accidents are
						of constant occurrencehas always been most in request amongst them, the
						danger seeming to be one of its chief recommendations. Working, eating, drinking, and sleeping together, and daily
						exposed to the same influences, these railway labourers soon presented a
						distinct and well-defined character, strongly marking them from the population
						of the districts in which they laboured. Reckless alike of their lives as of
						their earnings, the navvies worked hard and lived hard. For their lodging, a
						hut of turf would content them; and, in their hours of leisure, the meanest
						public-house would serve for their parlour. Unburdened, as they usually were,
						by domestic ties, unsoftened by family affection, and without much moral or
						religious training, the navvies came to be distinguished by a sort of savage
						manners, which contrasted strangely with those of the surrounding population.
						Yet, ignorant and violent though they might be, they were usually good-hearted
						fellows in the mainfrank and openhanded with their comrades, and ready to
						share their last penny with those in distress. Their pay-nights were often a
						saturnalia of riot and disorder, dreaded by the inhabitants of the villages
						along the line of works. The irruption of such men into the quiet hamlet of
						Kilsby must, indeed, have produced a very startling effect on the recluse
						inhabitants of the place. Robert Stephenson used to tell a story of the
						clergyman of the parish waiting upon the foreman of one of the gangs to
						expostulate with him as to the shocking impropriety of his men working during
						Sunday. But the head navvy merely hitched up his trousers, and said, 'Why,
						Soondays haint cropt out here yet!' In short, the navvies were little
						better than heathens, and the village of Kilsby was not restored to its wonted
						quiet until the tunnel-works were finished, and the engines and scaffoldings
						removed, leaving only the immense masses of débris around the line of
						shafts which extend along the top of the tunnel. In illustration of the extraordinary working energy and
						powers of endurance of the English navvies, we may mention that when
						railway-making extended to France, the English contractors for the works took
						with them gangs of English navvies, with the usual plant, which included
						wheelbarrows. These the English navvy was accustomed to run out rapidly and
						continuously, piled so high with stuff that he could barely see
						over the summit of his load, the gang-board along which he wheeled his barrow.
						While he thus easily ran out some 3 or 4 cwt. at a time, the French navvy was
						contented with half the weight. Indeed, the French navvies on one occasion
						struck work because of the size of the English barrows, and there was an
						émeute on the Rouen Railway, which was only quelled by the aid of the
						military. The consequence was that the big barrows were abandoned to the
						English workmen, who earned nearly double the wages of the Frenchmen. The
						manner in which they stood to their work was matter of great surprise and
						wonderment to the French people, who came crowding round them in their blouses,
						and, after gazing admiringly at their expert handling of the pick and mattock,
						and the immense loads of dirt which they wheeled out, would exclaim
						to each other, 'Mon Dieu, voila! voila ces Anglais, comme ils
						travaillent!'. Construction of Kilsby TunnelKilsby Tunnel at workOrdnance Survey maps and Signalling DiagramsIf you are wondering as to why Kilsby Tunnel has been
						included on a website dedicated to Warwickshire's railways, its because: a) we
						have a policy of starting and finishing each route with a significant station
						or location and Kilsby is certainly the latter; and b) as a child when I
						travelled by steam locomotive to Euston I was always mightly impressed by its
						length and massive ventilation towers; and c) as its my website I can say 'why
						not!!!!' 
 |