|
|
|
|
Building the last Main Line Railway
Newton to the Oxford Canal: gcrcs46
View of some of the temporary construction work required to
help bridge the Oxford Canal circa 1896. The vertical boiler on the left was
used to power the pumps that removed the water from the excavations for the
bridge abutments. The depth of these abutment foundations would be probably
fifteen to twenty feet deep even in the hard marl common to this area of the
county. The excavation would have required the driving of steel piles to create
a square box of a greater dimension than the foundation itself and then the
area inside would be excavated, probably by hand due to the limited room. A
concrete base would then be poured at the bottom and engineering bricks (hard
blue waterproof bricks) would be laid on top of this foundation to form the
actual abutment. Finally this would be capped with either stone or concrete to
form a hard standing for the steel girders with one end on bearings designed to
allow for movement.
back
|
|
|